Contaminated Soil Disposal & Cement Stabilisation 

Coffee Chain Drive Through, Derbyshire – May 2026 

A Midlands based design and build company were developing a drive through for a major coffee chain. The site investigation had identified localised hazardous waste soils which needed disposing of. The Ash team attended site and retrieved samples at depth and further delineated the extents. The onsite work comprised removing hazardous and inert soils. Ash Remediation staff are holders of the WAMITAB 4TMH COTC. This gives clients the assurance that waste is handled and disposed of correctly, this includes on site remediation which is also offered by Ash, details at: CIWM | Chartered Institution of Wastes Management UK 

The design also called for the formation level to have an increased bearing pressure. This was achieved via cement stabilisation which offered the required level of ground improvement. 

Contaminated Land Remediation 

Vale of Evesham – December 2025

A housing association contacted Ash remediation Management with a contamination issue at one of their properties. Building waste had been buried systematically over a number of years in a large garden. Soil analysis showed asbestos fragments as the main contaminant of concern although other debris was included. 

The remediation strategy employed by Ash was a labour-intensive hand picking and sorting exercise which uncovered much more material than the third-party investigation suggested. The waste was removed and a surface scrape of the area was completed, then certified clean top soil was reinstated.  

Ash Remediation management staff have the appropriate asbestos training to carry out these works; guidance can be found at: www.hse.gov.uk/asbestos  

Cement Soil Stabilisation

National Trust Scotney Castle, Lamberhurst – August 2026

Ash Remediation Management were approached by a prominent contractor in the Kent region whose prestigious client wanted to construct a multi terraced car parking facility. 

The site investigation carried out previously at the site identified soils with a weak bearing pressure which would need to be increased for the parking area and associated access roads. Members of the Ash team visited site and conducted a trial pitting operation across the potential working area. Samples were collected and laboratory tested against the TRL 447 Sulphate Suite. The testing proved that the host material was suitable for cement soil stabilisation. 

A dust free soil stabilisation mixing unit was used for the soil treatment and the ground was constantly watered to obtain the correct moisture content. The ground improvement was completed in ten working days including mobilisation/demobilisation. Expectations were surpassed on the final result with the bearing strength significantly higher than the minimum required. 

This is another demonstration of Cement soil stabilisation offering an effective and efficient ground improvement solution. 

Tank Decommissioning – South London

A builder of luxury homes acquired a former garage and fuel station site in South London. The site had 4 large foam filled tanks as well as an additional 11 tanks that were used for the storage of petrol, diesel and heating oil. All of these underground tanks and their associated infrastructure required cleaning, decommissioning and disposal.

Ash Remediation Management excavated and processed the foam filled tanks and cleaned, degassed and disposed of the remainder. The site was also probed and remnant structures were removed to facilitate the construction phase. The works were supervised by Ash Remediations’ WAMITAB certified staff and all local restrictions were adhered to without complaint from local residents or regulators.

Soil Stabilisation – East Anglia

A prominent regional construction firm had started work on a development but this was halted because of unforeseen ground conditions and encountering a wet fibrous soil with peat deposits. The majority of the site was too soft for plant to operate on, especially the piling rigs which were required in the later stages of the construction programme.

Ash Remediation Management stabilised the majority of the site down to a maximum depth of three metres. Soils were excavated and temporarily stockpiled whilst bases of the void were treated in-situ. The excavated material was treated ex-situ and then replaced and compacted in layers. 

CBR testing was carried out to verify the works and the end result was a geotechnically suitable piling mat and working platform (>30% CBR) which allowed the installation of the site infrastructure to continue. 

London

London Tank Decommission and Recycling

A former car mechanics yard was undergoing demolition to make way for a residential development. During the early stages of the demolition it was discovered that two underground storage tanks were present.

Ash Remediation Management were contacted who quickly and proficiently provided the means and expertise to degas, decommission and recycle the tanks.

The site, located in Central London posed a number of accessibility issues but Ash Remediation Management overcame these using their experience and carefully planning.

The tank decommissioning project was successfully completed with the efficient turnaround from project enquiry to completion minimising the delays to the remainder of the development project.

Bioremediation – Housing Development

Bioremediation Treatment Midlands

Ash Remediation Management were contacted by a Midlands based construction firm regarding approximately 1000m3 of contaminated soil that was encountered on their site. It was assumed that this material would have to be disposed of off site with clean fill imported, this however, was not the case.

Ash Remediation Management analysed the contaminated material and confirmed that a bioremediation process would be an effective and viable remediation route. The material was conditioned with compost and fertiliser before being laid on a bunded aeration system. The aeration system facilitated more efficient contaminant breakdown allowing the post treatment material to be available for use sooner. During the treatment phase biopile ‘health indictors’ (e.g. contaminant, O­2, CO2 concentration and temperature) were monitored to ensure the effectiveness of the treatment process.

The remediation programme was completed in 9 weeks.

University of Canterbury

Physical Stabilisation Canterbury

As part of the development of a new campus at the University of Canterbury, Ash Remediation Management carried out 11,000m2 of physical stabilisation. A CBR in excess of 30% was achieved with the project completed inside the required deadline.

Burnley Gasworks

Gasworks Waste Disposal

As part of the remediation of a former gasworks site, Ash Remediation Management provided a cost effective disposal solution to a variety of typical gasworks wastes including tar, PAH, TPH and cyanide. All aspects of the disposal work was managed by Ash Remediation Management and the project ran smoothly and completed ahead of the schedule.

Hampshire Technology College

Physical Stabilisation Hampshire

Due to a prolonged period of wet weather, ground conditions on site deteriorated which severely hampered the progress of our Clients development. Ash Remediation Management reacted promptly and carried out suitability testing and the subsequent physical stabilisation to achieve CBR values >5%. The improved ground conditions achieved by Ash Remediation Management allowed the development to ‘get back on track’ with minimal programme losses.